Blog Architecture practices
Fees versus hours: is this commission profitable before it is finished?
A commission pays if the hours it takes, times what each hour costs, stay below the fee. The hard part is knowing it halfway through, when it can still change anything.
Turn the fee into hours, by stage
If a stage is worth €12,000 and the average cost of an hour for the people working on it is €40, that stage has 300 hours before it loses money — fewer once you keep a margin. The figures are an example. Do it per stage: a job that looks fine overall can hide a stage that used twice its budget.
Where the margin goes
- Client changes — small one by one, large in total, rarely recorded.
- Site supervision that drags on — the build slips, the visits continue.
- Unlogged hours — calls, emails and coordination.
- Consultants and expenses — a margin based only on hours is incomplete.
How Fichaloto does it
Stages have their own dates, hours are logged against them and each project calculates its margin with individual costs and recorded expenses. Fichaloto for architecture practices.
Frequently asked questions
How is an architect’s hourly cost calculated?
Annual employment cost divided by the hours they can actually spend on projects, net of leave, holidays and internal time.
All of this is built into Fichaloto. See how it works.
Keep reading
How to choose
Twelve questions worth asking before you sign
None of these twelve questions is technical. Every one of them is answered in a sentence, and you can ask for the answers in writing before signing anything.
Compliance
A clocking record that cannot be quietly rewritten
Most time-tracking tools store hours in a table anyone with database access can edit. That is fine until the day somebody asks you to prove a number.
Capacity
Planned, clocked, charged: three numbers that should match and usually do not
Most companies can tell you what they planned and what they invoiced. Very few can tell you, for a given week, whether those two things are related.