Fees versus hours: is this commission profitable before it is finished?

5 min read

A commission pays if the hours it takes, times what each hour costs, stay below the fee. The hard part is knowing it halfway through, when it can still change anything.

Planned against logged hours by person and month, with overruns in amber and red
Real Fichaloto screen with sample data.

Turn the fee into hours, by stage

If a stage is worth €12,000 and the average cost of an hour for the people working on it is €40, that stage has 300 hours before it loses money — fewer once you keep a margin. The figures are an example. Do it per stage: a job that looks fine overall can hide a stage that used twice its budget.

Where the margin goes

  • Client changes — small one by one, large in total, rarely recorded.
  • Site supervision that drags on — the build slips, the visits continue.
  • Unlogged hours — calls, emails and coordination.
  • Consultants and expenses — a margin based only on hours is incomplete.

How Fichaloto does it

Stages have their own dates, hours are logged against them and each project calculates its margin with individual costs and recorded expenses. Fichaloto for architecture practices.

Frequently asked questions

How is an architect’s hourly cost calculated?

Annual employment cost divided by the hours they can actually spend on projects, net of leave, holidays and internal time.