Before accepting a project: how to check whether the team can deliver

5 min read

You need three numbers: the hours the project will need each month, the free hours your team has in those months, and a buffer. Almost nobody has the second one.

Planned workload by person and month, with months above 100% highlighted in red
Real Fichaloto screen with sample data.

A worked example

A team of six has 780 productive hours in March after holidays, leave and internal time. Current projects are allocated 640. That leaves 140. The new project needs 180 in March. It does not fit — and you would never see it by looking at headcount. The figures are illustrative.

Keep a buffer

Planning everyone at 100% guarantees that the first thing that slips is paid for by another project. Ten to fifteen percent unallocated is what absorbs change.

How Fichaloto does it

Capacity comes from each person’s working hours minus holidays and approved leave, allocations carry a percentage, and the coverage-gap view shows upcoming demand against what is left. Capacity planning.

Frequently asked questions

How much capacity buffer should a team keep?

As a rule of thumb, ten to fifteen percent unallocated, more when scope is loosely defined.

All of this is built into Fichaloto. See how it works.