Being allocated at a hundred per cent is not billing at a hundred per cent
Most arguments about utilization are really arguments about what is being measured, and nobody has said so out loud.
Three different rates with one name
When someone says «we are running at 85%», they could mean three quite different things. Worth separating them before setting any target.
- Allocated utilization. What share of available capacity is committed to something in the plan. It is a forecast: it looks forward and comes from allocations.
- Recorded utilization. What share of working hours actually got booked to a project. It is a fact: it looks backward and comes from timesheets.
- Billable utilization. What share of those recorded hours ends up on an invoice. It is the only one of the three directly tied to money, and it is always the lowest.
The denominator is where the cheating happens
The formula is simple: hours spent over hours available. The argument is always about the divisor.
Deduct before calculating anything: holiday, public holidays, known leave and committed training. If you do not, August looks catastrophic every year and means nothing.
Do not deduct, and instead absorb inside the target: internal management, business development, team meetings, pre-sales. That work exists, it is necessary, and somebody does it. Pulling it out of the denominator to make the number look better is self-deception.
The working rule: if the person could not have been on an engagement, out of the denominator. If they could and were not, in.
What target is reasonable
There is no universal number, but there is a universal mistake: applying the same target to everyone.
A junior can sit near 85% recorded utilization with nothing wrong, because the job is largely execution. A project lead hitting 85% is a warning rather than a win: it means they are not doing the part of the job that consists of reviewing, supervising and heading off problems. A partner running hot is a business development problem six months out.
And billable utilization always sits well below recorded. The gap between the two is your unbilled work: goodwill, rework, scope that crept in. Measured and watched, that gap tells you more than the headline rate does.
Why a hundred per cent is a bad idea
A team planned to 100% has no slack, and that produces three consequences that all arrive together.
Any delay propagates whole into the next engagement, because there is nowhere to absorb it. Nothing that walks through the door can be taken without pulling someone off something, and opportunities do not give six weeks' notice. And internal improvement work — documenting, automating, training — disappears, because there is never room and there is always something more urgent.
A target of 80–85%, with the remainder reserved deliberately, tends to produce more annual margin than chasing 100%, precisely because it leaves room to react.
Frequently asked questions
Does training count as utilization?
As billable utilization, no. As available capacity it depends on whether it was mandatory and committed in advance: if so, take it out of the denominator like any other absence. What you should not do is leave it in and then complain the number is low.
How do you measure it when not everything is project work?
Create an internal project for non-client work and book to it. It sounds bureaucratic and it is the opposite: it is the only way to find out how much internal work actually weighs, which in many firms turns out to be a quarter of the year.
How often should it be reviewed?
Recorded, monthly — any shorter and it does not mean anything yet. Allocated, weekly, because that is what tells you who comes free and how much warning you get. Watching recorded utilization weekly generates anxiety rather than decisions.
All of this is built into Fichaloto. See how it works.
Keep reading
Capacity
Planned, clocked, charged: three numbers that should match and usually do not
Most companies can tell you what they planned and what they invoiced. Very few can tell you, for a given week, whether those two things are related.
Capacity
The resourcing meeting costs more than you think
Nobody budgets for this meeting. It is the most expensive one you run and the one that produces the fewest decisions per minute spent.
Capacity
Before accepting a project: how to check whether the team can deliver
You need three numbers: the hours the project will need each month, the free hours your team has in those months, and a buffer. Almost nobody has the second one.